The kitchen remodel is moving right along Water bubblers are installed We scoped out where new sanctuary lighting will shine Fire suppression pipes are now in place up in the [...]
The thick concrete and reinforcement metal that made up the small stage in Fellowship Hall was cut up and hauled out today.
Staging build started today!
Windows are being measured. Electrical work is underway.
A beautiful new Princeton Elm tree (grown in Buffalo, NY) was planted near the Memorial Garden. New kitchen plumbing went in.
Pews have been remover. The sanctuary floor is opened up. Accessible bathroom is ready for plumbing.